Well, no letter has arrived as
yet confirming that East Windsor
Cogeneration Properties Inc (or
its parent, sister etc.) ) will
pay lawyer #1's legal fees. But I
receive an information card from
EWCC (East Windsor Congeneration
Centre) providing its building
schedule. The schedule is as
follows:
October 2007
Start of Preconstruction
activities
November 2007 - Piling
work
December 2007 - Excavation and Foundation
work
2008 Ongoing Construction
March 2008 - Onsite Building
Construction & Equipment Installation
2009
Spring 2009 Start of Commissioning
September 2009 - Start of Operations
If you have not done so as yet,
please read my post titled,
Legal Fees